Non-Process Infrastructure
CC0004 – Early Earthworks
Contractor: Allan-Cash Metis Construction JV
This package supports the early execution of earthworks. The scope covers expansion of the SWEF (Shaft Waste Effluent Facility) pond, construction of early laydown areas and modification of the rural municipality road.
CC1601 – Vent Plenums Phases 2 and 3 (substations civil works)
Contractor: Graham Industrial Services LP
The scope of this contract centres around the following work fronts:
- Foundations for the vent plenums phases 2 and 3 at the DV (Dalla Valle) shaft and service shaft
- Foundations for the 230-kilovolt and 34.5-kV substations
- Foundations for the cable bus between the substations
- Foundations for the harmonic filters and modular data centre
CG2703 – Coarse TMA Phase 1AB
Contractor: Allan Ventures Development Corp.
Stripping of Horizon A, construction of dykes and associated instrumentation, decommissioning of five (5) monitoring wells, installation of two (2) monitoring wells, installation of piping for three (3) interceptor ditch pumps, modification of existing sewage effluent, reject water, and dewatering line.
- Earthworks for existing disposal well B, earthworks for pipeline from disposal well B to disposal well A, and earthworks for disposal well A
- Earthworks for rail section from loadout building to disposal well A
- Installation of environmental monitoring station
CC0003 – Earthworks
Contractor: Ledcor CMI Ltd.
Earthworks associated with stripping, mass excavation and drainage ditching, road construction, foundation ‘bath-tubbing’, and laydown development. The buried services work includes trenching and the installation of the site’s main distribution networks for natural gas, raw water, potable water, fire water, storm water, sewage (gravity and pressurized), and dewatering.
CG2802 – 230kV & 34.5kV Substations and Power & Communication Distribution
Contractor: PCL Industrial Management
Construction of substations, E-house, two Modular Data Centers, as well as site power and communications distribution.
CG2902 – Potable Water Treatment Plant and Diesel Fuel System
Contractor: Deep River Contracting JV
SMPEI (Structural Mechanical Piping Electrical Instrumentation) modifications to existing PWTP buildings.
Site services
SC6206 – Site Civil Inspection and Testing
Contractor: SNC Lavalin Inc.
This package involves the testing of earthworks, fill material, concrete and grout to support quality assurance assessments and inspections.
SC6204 – Site Survey
Contractor: GeoVerra Inc.
This package involves the EPCM (engineering, procurement, construction management) work beginning the second quarter of 2021 covering project site surveying. Part of the scope includes the pre-sanction funding. The duration spans the second quarter of 2021 (Q2 2021) to the third quarter of 2026 (Q3 2026) and includes:
- Construction and industrial surveying
- Support for validation of invoiced earthwork quantities
- Updating the three key master plans for site topography, buried services, and facilities
- Survey for engineering/design confirmation requirements
- Survey assurance activities or data collection in addition to survey data collected by construction contractors, as required
SC6105 – Concrete Batch Plant
Contractor: LaFarge Canada, Inc.
Design/proposal, supply, construction/installation, commissioning, and start-up of a concrete batch plant which is to be demobilized from site upon completion of the work.
SD6501 – Busing
Contractor: Wicehtowak Employee Transportation Ltd.
Provision of fully maintained and operated buses and the provision transportation services to transport JS1 employees to and from the Jansen Site and locations in Saskatoon and Regina.
Process
CC0001 – Piling
Contractor: AECON
This package includes installation of the drilled concrete piles for the project. The scope includes all process buildings and final piles around the headframes.
CM2001– Rail Mounted Machine Design
Contractor: FAM Canada Inc.
Supply and installation package of the reclaimers in the Raw Ore and Product Storage buildings.
CA2001– Raw Ore / Product Storage Building Design / Build
Contractor: CoverCo.
Design, fabrication, delivery, construction and commissioning of the Raw Ore and Product Storage Buildings.
CC2001– Mill Area – Foundations
Contractor: Aecon Industrial Management
Supply all of the labour, materials, equipment, tools, and supervision to execute the mill building foundations.
Mining
CG1001 – DVS and SS Post Liner Excavation, Steel and Equipping
Contractor: Cementation Canada Inc.
This package will equip the service shaft for future production and the DV (Dalla Valle) shaft for construction of the underground mine.