Awarded contracts

BHP is grateful for all companies that submit competitive bids for our contracts and procurement. Below is a list of the most recently awarded contracts. 

Non-Process Infrastructure

Package Number
Description
Contract Approval
Contract Execution
Contract Mobilization
Fine TMA / Course TMA Phase 1B / Onsite Rail - Earthworks
Mid-January 2022
February 2023
July 2023
Tailings and Development Spoils (DS) systems SMPEI
February 2022
November 2022
December 2023
Onsite Rail and Joint Access Spur
January 2022
June 2022
July 2023
Assembled Junction Boxes/Misc. Cabinets
October 2023
November 2023
Not Applicable
APC Software - Plant Performance Monitoring (ATP)
October 2023
December 2023
Not Applicable

CC2701 – Fine TMA / Course TMA Phase 1B/ Onsite Rail – Earthworks

Contractor: 2 Nations Bird Contruction LP

The scope of work includes the construction of the fine tailings storage facility. Within the facility the scope also includes the construction of two concrete decant towers, the fine brine transfer pumpstation, and several interceptor ditch pumps. HDPE pipe scope included the toe and finger drains installed within the dykes, the extensive underdrain piping network, and the brine transfer lines from the Fine Cell to the Coarse Tailings Cell. Scope also includes the supply and installation of the interceptor ditch pumps, brine transfer pumps, and associated electrical and instrumentation equipment and ancillaries.

CG2704 – Tailings and Development Spoils (DS) systems SMPEI

Contractor: Centurion Canada Infrastructure Inc

The scope of work includes the installation of the DS temporary equipment. It also includes the SMPEI installation of the tailings facilities, including the brine reclaim barge, surface HDPE pipelines, brine disposal well stations, e-houses, pumps, and all associated electrical and instrumentation equipment and wiring. Scope also includes the design, supply and installation of temporary Electrical and Control houses, design to be based on Team Jansen provided performance specifications, and engineering. DS is used to address early mine development in advance of Mill construction and commissioning.

CR3101 – Onsite Rail and Joint Access Spur

Contractor: A&B Rail Services LTD

This work includes supply and fabrication of material for the rail superstructure and area lighting as well as
connection of the signalling and tower control to the main site networks; installation of the superstructure, rail signalling and tower control system.

PJ0007 – Assembled Junction Boxes/Misc. Cabinets

Contractor: Community Electric LTD

Supply, fabrication and testing of Instrument power distribution panels and communication cabinets based on the panel layout drawings and Bill of Materials provided, as well as Project specifications and industry standards for the following areas: Instrument Power Panels, Communication Cabinets, Data Logger.

PJ0019 – APC Software – Plant Performance Monitoring (ATP)

Contractor: Valmet LTD

Supply of PlantTriage software which is plant performance monitoring software and one (1) year of Software Maintenance and support.

Site services

Package Number
Description
Contract Approval
Contract Execution
Contract Mobilization
Dry Mill PAU Heavy Haul
June 2022
October 2022
September 2023
Heavy Lift and SPMT
June 2022
October 2022
August 2023

SG6101 – Dry Mill PAU Heavy Haul

Contractor: RHG Transport and Consulting Inc. O/A NEXTGEN Transportation LTD

The scope includes:

  • Provision of heavy haul transportation services from PAU assembly facilities (Dry Mil Area and Robot Product Loadout PAUs) to Jansen Site in support of Dry Mill Area SMPEI Contract.
  • Preassembled Units: Fabrication and Assembly;
  • Transportation permitting;
  • Preparation of transportation plans and transportation drawings;
  • PAU weighing and provision of weighing reports;
  • Provision and delivery of shipping beams and shims to PAU assembly facilities

SG6103 – Heavy Lift and SPMT

Contractor: RHG Transport and Consulting Inc. O/A NEXGEN Transportation LTD

The scope includes:

  • Provision and operation of four heavy lift cranes at the Mill Building Area.
  • Provision and operation of four trains of SPMT to transport PAUs from the Jansen Site laydown to the Mill Building Area work-fronts.
  • Provision and installation of crane mats for heavy lift crane and SMPEI crane operation at the Mill Building Area.

The SG6103 Heavy Lift and SPMT contractor will render these services in support of Mill Building SMPEIs Dry Mill Area SMPEI and Wet Mill Area SMPEI contracts.

Process

Package Number
Description
Contract Approval
Contract Execution
Contract Mobilization
Dry Mill Area
May 2022
September 2023
November 2023
Preassembled Units Fabrication and Assembly - Dry
February 2022
July 2022
September 2023

CG2101 – Dry Mill Area

Contractor: Worleycord LP

The Scope of Work is for the installation of preassembled units (PAU) and construction of Structural, Mechanical, Piping, Electrical and Instrumentation (SMPEI) components in the Dry Mill and Screening areas and includes , general consumables, temporary supports, concrete, some equipment, electrical, instrumentation, and architectural.

CG2002 – Preassembled Units Fabrication and Assembly – Dry

Contractor: Worleycord LP

The scope of the package covers assembly of all PAUs within the Dry, Screening and Product Loadout areas (Robot PAUs) including fabrication of all stick build piping. Assembly scope includes all structural steel, elevated concrete slabs, mechanical equipment, piping, electrical, and instrumentation. Supply scope includes, general consumables, temporary supports, concrete, some structural bulks, electrical, instrumentation, architectural, and robot equipment.

Mining

Package Number
Description
Contract Approval
Contract Execution
Contract Mobilization
Service Shaft Headframe Changeover
Early November 2021
March 2022
May 2023

CG1601 – Service Shaft Headframe Changeover

Contractor: Ledcor Projects Inc.

The scope includes the changeover of the Service Shaft (SS) headframe, installation of the permanent mine ventilation systems, and surface raw ore handling infrastructure. The SS headframe changeover involves removal of the existing sinking headframe and installation of a permanent production headframe.