Upcoming contracts

A complete list of upcoming contracts for the Jansen project, covering Non-process infrastructure, Site services, Process and Mining can be found below.

* The timelines provided are estimates and may be subject to change

Non-Process Infrastructure

Package Number
Description
Estimated Pre-Qualification Start
Estimated RFP Issue
Estimated Award
Integrated Operation Centre (IOC)
March 2023
September 2023
April 2024
Pre-Engineered & Modular Buildings - Package 1
Decembe 2022
January 2024
September 2024
Pre-Engineered & Modular Buildings - Package 2
December 2022
June 2024
May 2025
Tailings and development spoils (DS) system SMPEI (Structural, Mechanical, Piping, Electrical and Instrumentation)
February 2022
November 2022
December 2023

CA2911 – Integrated Operation Centre (IOC)

The scope of work includes the fit-out, renovation, construction, commissioning, and turnover of the Jansen Stage 1 IOC and 3 floors of general office space:

  • General purpose office space is leased by BHP with an approximate area of 1,746 m2 per floor.
  • The renovation includes a control room area as well as the balance of IOC office/collaboration areas and associated infrastructure including electrical, HVAC, communications, and audio-visual elements.

CG2804 – Pre-Engineered & Modular Buildings – Package 1

The scope of work for package CG2804 – Package 1 (NPI buildings), includes the supply (fabrication and delivery to site), installation, construction and commissioning the entire building and building systems listed below:

  • Emergency Response and Mine Rescue Facility (repurposed freeze plant)
  • Admin, Mine & Mill dry building (new building)
  • Heated Warehouse (new building)
  • External Works.

CG2805 – Pre-Engineered & Modular Buildings – Package 2

The scope of work for package CG2805 – Package 2 (NPI buildings), includes the supply (fabrication and delivery to site), installation, construction and commissioning the entire building and building systems listed below:
Maintenance & Workshop, Heavy/Light Vehicle Maintenance, Mill Support, Laboratory, Rail Support Facility, Enclosed Walkway and External Works.

CG2704 – Tailings and development spoils (DS) system SMPEI (Structural, Mechanical, Piping, Electrical and Instrumentation)

This scope of work includes the installation of the DS temporary equipment. It also includes the SMPEI installation of the tailings facilities, including the brine reclaim barge, surface HDPE pipelines, brine disposal well stations, e-houses, pumps, and all associated electrical and instrumentation equipment and wiring. Scope also includes the design, supply and installation of temporary Electrical and Control houses, design to be based on Team Jansen provided performance specifications, and engineering. DS is used to address early mine development in advance of Mill construction and commissioning

Site services

Package Number
Description
Estimated Pre-Qualification Start
Estimated RFP Issue
Estimated Award
Wet Mill PAU Heavy Haul
June 2022
October 2022
February 2024

SG6102 – Wet Mill PAU Heavy Haul

The scope of this package includes:

Provision of heavy haul transportation services from PAU assembly facilities (Wet Mil Area) to Jansen Site in support of Wet Mill Area SMPEI Contract.

Preassembled Units: Fabrication and Assembly;

  • Transportation permitting;
  • Preparation of transportation plans and transportation drawings;
  • PAU weighing and provision of weighing reports;
  • Provision and delivery of shipping beams and shims to PAU assembly facilities

Process

Package Number
Description
Estimated Pre-Qualification Start
Estimated RFP Issue
Estimated Award
Dry Mill Area
May 2022
September 2022
November 2023
Wet Mill Area
July 2022
December 2022
February 2024
Ducts
January 2022
September 2022
December 2023

CG2101 – Dry Mill Area

The scope of work is for the installation of preassembled units (PAU) and construction of Structural, Mechanical, Piping, Electrical and Instrumentation (SMPEI) components in the Dry Mill and Screening areas and includes , general consumables, temporary supports, concrete, some equipment, electrical, instrumentation, and architectural.

CG2102 – Wet Mill Area

The Scope of Work is for the installation of preassembled units (PAU) and construction of Structural, Mechanical, Piping, Electrical and Instrumentation (SMPEI) components in the Wet Mill areas and includes , general consumables, temporary supports, concrete, some equipment, electrical, instrumentation, and architectural. 

PM0015 – Ducts

Supply of detailing, engineering, steel, procurement, steel fabrication, testing, surface preparation and protective/insulative coating, and packaging for shipment.

Mining

Package Number
Description
Estimated Pre-Qualification Start
Estimated RFP Issue
Estimated Award
Mobile Equipment - Roller Change-out Attachment
September 2018
December 2021
February 2024
Mine Load Centres (VPT)
February 2023
April 2023
November 2023
Mining UG Construction SMPEI
June 2022
March 2023
August 2024

PM1134 – Mobile Equipment – Roller Change-out Attachment

Roller Change-out attachment to lift the conveyor belt weight off the rollers so maintenance personnel can switch out rollers.

PE1105 – Mine Load Centres (VPT)

Supply of engineering, detailing, procurement, fabrication, assembly, testing and packaging for shipment of 2 types of Mining Underground Equipment:

  • Panel Friction Monorail System (FMS) including 15kV festoon, Mine Load Centres and motorized trolley system to supply power and communications to the PM1130 Borer and EBS System.
  • Disconnecting and Transformation Sled (DTS).

It also includes fabrication, assembly, and packaging for shipment of the S5x10 monorail beams included in the PM1130 borer system
VPT design.

CG1102 – Mining UG Construction SMPEI

This package is to support mining ramp up, installation of permanent mine infrastructure and equipment with staged commissioning, and handover to BHP Operations. The scope includes the execution of the structural, mechanical, piping, electrical and instrumentation (SMPEI) works critical to first production.

The Scope of Work also includes:

  • Raw Ore and Surge bins (including bin excavation).
  • Permanent Bulk Material Handling (BMH) conveyors.
  • Facilities
  • Underground electrical substation.

Operational Readiness

Package Number
Description
Estimated Pre-Qualification Start
Estimated RFP Issue
Estimated Award
MRO (Multiple supplier opportunities)
February 2024
March 2024
July 2024
Rebuilds (Multiple supplier opportunities)
July 2024
September 2024
January 2024
Site security
November 2024
November 2024
January 2025
3rd Party rail yard Operations and Maintenance - Jansen
April 2025
April 2025
July 2025
Customs and Brokerage Service Agreement
July 2025
July 2025
October 2025
On-site Materials movement contract
December 2024
December 2024
March 2025
3PL & OSR Logistics Strategy
March 2024
March 2024
June 2024
Rebuild Strategy including Precision repairs/rebuilds (PRC046)
July 2025
August 2025
October 2025
OEM Parts and Services
February 2024
March 2024
April 2025
Maintenance Services Strategy
March 2026
March 2026
May 2026
Mechanical HD MSA Labour
TBC
TBC
TBC
HVAC Services
April 2025
March 2025
June 2025
High Voltage Services
June 2025
July 2025
August 2025
Loadout Automation Services
TBC
TBC
TBC
Conveyor Services
July 2025
August 2025
October 2025

Ops Scope – MRO (Multiple supplier opportunities)

The MRO Parts and Consumables scope is comprised of the following elements: workplace safety equipment, PPE, tools, electrical and mechanical, adhesives and lubes, office consumables, lab equipment and apparel.

The scope will also include:

  • Technology integration
  • Standardizing processes
  • Continuous improvement
  • Reporting analytics
  • Emissions reductions through de-carbonization targets

Ops Scope – Rebuilds (Multiple supplier opportunities)

The scope of this package includes the provision of rebuild services for a variety of equipment. On a high level this will require the contractor to diagnose the conditions of the item to be rebuilt, procure the materials needed to rebuild, provide the rebuild services, and report on any testing or quality requirements. We expect most of this work to occur off-site at the Contractors location.

Ops Scope – Site security

Provision of Site Security for Potash and identified facilities.

Ops Scope – 3rd Party Rail yard Operations and Maintenance at Jansen

The 3rd party rail operations and maintenance scope are critical to ensure safe and efficient rail operations. This scope encompasses management of rail operations at Jansen as well as light maintenance and movement of railcars around Jansen.

Ops Scope – Customs and Brokerage Service Agreement

Customs and brokerage services to support Jansen operations. Primary users will be Rail (movement of railcars into and from US) and WIL (e.g. sending repairables/rebuilds into US as required)

Ops Scope – On-site Materials movement contract

Movement of operational materials between onsite surface warehouse and delivery points across the Jansen mine site. Excludes movements of materials underground. 

Ops Scope – 3PL & OSR Logistics Strategy

Captures Jansen inbound supply chain. Deliverable encompasses two pillars: warehousing (comprising warehousing, consolidation, and storage of materials), and freight.

Ops Scope – Rebuild Strategy including Precision repairs/rebuilds (PRC046)

The scope of this package includes the provision of rebuild services for a variety of equipment. On a high level this will require the contractor to diagnose the conditions of the item to be rebuilt, procure the materials needed to rebuild, provide the rebuild services, and report on any testing or quality requirements. We expect most of this work to occur off-site at the Contractors location.

Ops Scope – OEM Parts and Services

We have 110 OEMs that Jansen will require parts supply and select services from. Some sooner than others. Commercial will use the same scope for all 110 OEMs. Goods and Services contract. of this work to occur off-site at the Contractors.

Ops Scope – Maintenance Services Strategy

Jansen requires a variety of maintenance services. . For OEM services that also require parts supply – these will be captured under the OEM parts and services project.

Ops Scope – Mechanical HD MSA Labour

Jansen site requires complete inspection and repairs of all diesel based surface mobile equipment. This includes service/use of their equipment to flatdeck/transport to an offsite shop for larger repairs. Ability to turnaround repairs is also required.

Ops Scope – HVAC Services

Jansen site needs complete inspection and repairs of all HVAC systems on site.

Ops Scope – High Voltage Services

Jansen requires complete inspection and repairs on overhead lines, high voltage transformers and other high voltage work beyond Jansen’s capabilities.

Ops Scope – Loadout Automation Services

Jansen site requires specialty inspections and repairs on loadout automation assets. Will include rebuild scope if applicable.

Ops Scope – Conveyor Services

Services and parts associated to the maintenance of Conveyors on site.